Here is today's effort. The right front frame has been profiled to shape and attached to the main frame.
There is a little more fine tuning to the shape but it is close. The boss surrounding the shaft bearing is 1" diameter and will be reduced to about 7/8" after the clutch actuator assembly is mounted and the bearing cap will be profiled to match the rear hoist bearing cap. I didn't get to left hand frame. that will be for tomorrow.
I also decided it was time for a partial assembly to check clearances and alignment. The main things that I needed to check was clearances, alignment and gear mesh.
All went well except that both eccentric straps needed a stoke or two of the file to reduce the thickness and eliminate some binding. The gear mesh of the front drum to the pinion was what I was most worried about and a little file adjustment to the mating surfaces on the front of the main frame and the rear of the front frame. It is now perfect. (I'll be the judge of that)
Another big reason for the assembly is to help visualize the location of all of the mechanism inside the frame. There are two brake linkages, operated by foot pedals, and two ratchet linkages, operated by hand levers. The ratchet pawls are lifted into the ratchet teeth through a coil spring so that it can over ride in one direction and lock in the other direction.
I don't have any plans for this and the machine that I am using for reference has lost almost all of this through age and rust. It is also very difficult to get under the thing to do any measuring.
Thanks for watching. 27329
Jerry