Well , it's pretty obvious that the rear stop has to be at thesame distance from the pivoting point as the front stop , but on the right rear side .
That puts both stops symetrical around the lever screw and creates some kind of scissoring effect .
On ausdier's plans that would put the bore at 25mm from the rear end instead of 5mm .
Putting the second stop there makes the lever/leverlink combination work the way I think it should . But then the right rear stop interferes at some point with the vice .
Depending on the size of the dies this will be a problem or not .
I'l look into that once I get some dies done .
A few minor errors I found in Ausdier's plans :
Vice moveable jaw mount : 20mm has to be 21mm .
found out he hard way
Base : 12.7 mm has to be 13 or 19mm has to be 18.7
Otherswise the vice doesn't sit against the reces milled in the base
Base : dimensions of the long hole with is missing . 5 and 10 mm
Lever : Dimension for the front M3 hole hole : 45mm from the right side .
Dimension of the rear M3.hole : 25mm from the right side
Stop : length is missing : 30mm .
I really enjoyed maching the parts using this plan .
The 3D view makes life so much easier .
@Ausdier , what software package did you use to draw them ?
Here's a couple of pictures of what I've got sofar .
Needs some finishing touches here and there , but you get the general idea .
Next I'm gonna have to make me some dies , but that will take a while .
I'll need to make a tangential toolholder for the lathe first .
Btw , the block and lever screws were turned using a
vertical shear tool for the finish .
For those who don't know what it is ( I didn't ) do a youtube search for a video uploaded by mrpete222. The tool is really amazing and it's just a HSS toolbit ground in a special way .
Pat
.
.